TECHNICAL ASSISTANCE FOR ENGINEERING, SUPERVISION AND SITE MANAGEMENT

By TCN PMU,

  Filed under: Breaking News, Expression of Interest (EOI), Featured Projects, Latest News
  Comments: None

 

 

 

 

 

 

NIGERIA ELECTRICITY TRANSMISSION PROJECT (NETAP)

 

 

 

 

 

TERMS OF REFERENCE (TOR)

 

 

 

for

 

 

 

TECHNICAL ASSISTANCE FOR ENGINEERING, SUPERVISION AND SITE MANAGEMENT OF RECONDUCTORING OF NTP-TR5G AND NTP-TR5E TRANSMISSION LINES

 

 

 

PREPARED

 

 

 

BY

 

 

TRANSMISSION COMPANY OF NIGERIA (TCN)

PROJECT MANAGEMENT UNIT (PMU)

NO, 10, KUNENE CLOSE, OFF BOBO STREET

OFF GANA STREET, MAITAMA ABUJA.

 

 

 

 

 

NOVEMBER 2020

 

 

 

 

 

 

 

1.0       BACKGROUND

 

The Federal Government of Nigeria has received a credit on behalf of Transmission Company of Nigeria (TCN) from the International Development Association (IDA) under the World Bank towards the cost of Nigeria Electricity Transmission Project (NETAP).  The Company, therefore, intends to apply part of the proceeds of this credit for payments under the Contract for Engineering Supervision and Site Management of Reconductoring of Transmission Lines Projects (NTP-TR5G and NTP-TR5E).

 

The Nigeria Electricity Transmission Project (NETAP) seeks to redress certain deficiencies and operational constraints of the Nigeria Power Transmission System to allow the efficient dispatch and transmission of Power in the National Grid through additional transmission capacity.  In particular, it will complement efforts under-way for both emergency and long-term measures now being taken to increase generation.

 

Part of the NETAP investment component includes the contracts for the Engineering Supervision and Site Management of the reconductoring of Transmission Lines.  An Engineering consultancy service is therefore required to manage and supervise the works covered under the contracts as mentioned above.

 

The Project management and supervision Consultant to be engaged by TCN will assist its project implementation Unit (PIU) among others in the overall supervision of the 132kV Transmission Line reconductoring Projects Management and Supervision. The Consultant will as well assist the Project Management Unit of TCN in the procurement and inspection of all necessary line material needed for the full implementation of the Project, Construction coordination, quality assurance, safety compliance and testing/ commissioning of the line project.

 

1.1       Status of the Project

 

The TCN carried out studies on its existing transmission network, and some lines were identified as being old and weak and needed uprating and upgrading for a stable and reliable power supply. The lines under consideration are:

 

S/N

TRANSMISSION LINES

LOCATION

1.

Kumbotso - Hadejia 132kV Single Circuit Transmission Line (165km)

North West

2.

Kumbotso - Kankia 132kV Single Circuit Transmission Line (100km)

North West

3.

Benin - Irrua 132kV Single Circuit Transmission Line (81km)

South-South

4.

Irrua - Okpella 132kV Single Circuit Transmission Line (65km)

South-South

5.

Okpella - Okene 132kV Single Circuit Transmission Line (43km)

North-Central

6.

Okene - Ajaokuta 132kV Single Circuit Transmission Line (52km)

North- Central

7.

Port Harcourt Main - Port Harcourt Town 132kV Double Circuit Transmission Line (6km)

South-South

8.

Alaoji - Abba Town 132kV Single Circuit Transmission Line (8km)

South East

9.

Osogbo - Offa - Omuaran - Ganmo - Ilorin 132kV Single Circuit Transmission Line               (150km)

South West

10.

Onitsha – Oji River 132kV Single Circuit Transmission Line

South East

 

11.

 

Gombe - Biu - Damboa - Maiduguri 132kV Single Circuit Transmission (356km)

 

North-East

 

 

The summary of the contracts NTP-TR5G and NTP-TR5E which are in four (4) lots which shall be managed and supervised by the Consultant under the project assignment as below:

 

               NTP-TR5G  (LOT 1)

                        Kumbotso - Hadejia 132kV SC Transmission Line

                        Kumbotso - Kankia 132kV SC Transmission Line

 

               NTP-TR5E (Lot 1)

                        Benin - Irrua 132kV SC Transmission Line

                        Irrua - Okpella 132kV SC Transmission Line

                        Okpella - Okene 132kV SC Transmission Line

                        Okene - Ajaokuta 132kV SC Transmission Line

 

               NTP-TR5E (Lot 2)

                        Port Harcourt Main - Port Harcourt Town 132kV DC Transmission Line                                  Alaoji - Abba Town 132kV SC Transmission Line

                        Osogbo - Offa - Omuaran - Ganmo - Ilorin 132kV SC Transmission Line

                        Onitsha – Oji River 132kV SC Transmission Line                                                   

               NTP-TR5E (Lot 3)

                        Gombe - Biu - Damboa - Maiduguri 132kV SC Transmission

 

 

2.0       OBJECTIVE OF THE TERMS OF REFERENCE

 

The objective of this TOR is to seek the services of a qualified and experienced firm that is specialized in power system development and operations with vast experience in the Design and Construction of  High Voltage Transmission Line (132kV and above) to be engaged to assist TCN's Project Management Unit (PMU) in the implementation of the Transmission Line reconductoring project.

 

2.1       The objective of the Consultant's assignment is to assist in the management and supervision of works required in the implementation of the Contract for the reconductoring of 132kV Transmission Lines under NTP-TR5G and NTP-TR5E contracts.

 

Generally, the Consultant shall work hand in hand with the Employer's Engineers in the execution of all aspects of the assignment.  The Employer must endorse certifications made on documents and drawings by the Consultant.

 

2.2       During the execution of this assignment, the Consultant will be required to take inputs from a broad field of expertise covering the following:

 

  • Project Administration and Control.
  • Supervision of the Performance of the Contractors handling NTP-TR5G and NTP-TR5E contracts.
  • Supervision of installations up to commissioning and handing over of works under NTP-TR5G and NTP-TR5E contracts.
  • Training of TCN staff and transfer of skills.

 

2.3       The Consultant's works shall be executed per requirements of the tender documents for reconductoring of 132kV Transmission Lines under NTP-TR5G and NTP-TR5E.

 

2.4       The Consultant will be required in the course of carrying out this assignment to coordinate and monitor all other project works associated with the contracts NTP-TR5G and NTP-TR5E, which shall be executed concurrently at the affected sites.

 

2.5       The Consultant shall perform his assignment until the end of defects liability period of twelve (12) months after the provisory take-over from the Contractors of the Project works carried out under NTP-TR5G and NTP-TR5E contracts.

 

 

 3.0      SCOPE OF SERVICES

 

The Consultant to be engaged shall provide overall management on all aspect of works/services for the design, manufacturing, testing, supply, delivery to site of GzTACSR conductors, Composite Insulators and OPGW, including all associated fittings, complete composite insulator sets, phase and earth-wire tension and non-tension joints and clamps and vibration dampers. The assignment will also involve the testing and the rehabilitation of existing towers and improvement of earthing where necessary. It will also require the undertaking of erosion control on existing towers where necessary.

 

The scope of works covered under NTP-TR5G and NTP-TR5E contracts which are in four (4) lots are as follows:

 

  • Project Management and Supervision

 

The Consultant shall:

  • Manage overall liaison between the Employer and the Contractors
  • Review and approve all the engineering drawings, diagrams and documents submitted for approvals on the Contracts for NTP-TR5G and NTP-TR5E project works in accordance with contractual and engineering specifications
  • Assist the Employer in any issues relating to Contract, especially compliance with the matters with a performance bond, insurance, and claims; and to prepare certain documents that may be required by the World Bank.
  • Lead progress and site meetings prepare agendas and write minutes of meetings, periodical follow-up reports and take-over reports.
  • To oversee follow-up, periodical updating and coordinate work schedules of the contractors handling all the projects in the four transmission lines.
  • Prepare monthly, quarterly progress and project completion report for the contracts per the World Bank requirements.
  • Verify quantities of works performed and shall certify invoices issued by contractors in conjunction with the Employer's Engineer on the Project.
  • Make sure that supplies and works planning to comply with schedules in the actual Contract supply and work progress on-site following contract Schedule and determine where necessary, suggest measures to be taken to speed up the works.
  • Examine any change/deviation of specifications or variations in the scope of work as stipulated in the tender documents which are proposed by the Contractors and make recommendations to the Employer for approval of the change of specifications and variation of scope with the resultant cost adjustment.
  • Follow-up damage reports and ensures that damaged materials are subsequently replaced.
  • Check and approve the Contractors quality assurance applied by all the contractors during works execution
  • Monitor the implementation of social, environmental, health and safety standards and requirements as specified in the ESMPs, and RAPs (if applicable) and monitoring any instance of gender-based violence, and reporting non-compliance to the owner and proposing mitigation measures
  • Issue Provisional Acceptance Certificate after commissioning and the Final Acceptance Certificate after the expiration of the Guarantee Period.

 

  • Technical Control of Designs

 

The Consultant will verify if calculations and hypotheses used, construction drawings, diagrams and documents submitted for his approval are worked out following contractual and engineering specifications.  Emphasis shall be put on the following tasks:

 

  • Design and manufacture of the fittings - parts/accessories shall be such that they shall be completely compatible with the GzTACSR conductor - a high-temperature low sag (HTLS) type conductor and smoothly fitted with the existing fittings/parts not to be replaced on the existing Transmission Line.
  • Inspection of shipped materials before their use
  • Checking the final technical as-built documentation prepared by the Contractors.

 

  • Receipt of the equipment in factory and supplies to the site

 

The Consultant shall:

 

  • Verify conformity of equipment with contract specifications
  • Examine any change/deviation to the contract specifications that might be proposed by the Contractors
  • Check and approve the Contractor's Quality Assurance Plan
  • Check and approve factory testing and inspection program in factory proposed by the Contractors/Suppliers
  • Ensure that equipment has undergone testing as requested in the Contract and that the contractor submits test certificate to the Consultant for approval.
  • Plan and supervise all Factory Acceptance Test (FAT), and all tests carried out by the contractors at site and sign such test reports.
  • Participate in "routine testing" for major equipment together with the Employer's Engineer at the manufacturer's works
  • Regularly check the program for production and delivery to the site of the main equipment to ensure timely completion of the Contract according to schedule.
  • Review the operation and maintenance manuals provided

 

At the commencement of Project, the Employer shall specify to the Consultant,     a list of the primary materials that must be inspected by them in the factory             together with the Employer's Engineers.

 

3.4       Pre-Commissioning Tests and Commissioning Upon Works Completion

 

On works completion, the Consultant shall supervise the pre-commissioning tests and the final commissioning of all works.  The Employer's Engineers shall assist the Consultant.

 

The Consultant shall establish with each of the contractors and with approval of Employer, commissioning, and testing procedures for each of the concerned Project defining:

 

  • The role and the responsibility of each of contracting parties.
    • Tests to be carried out for the projects
    • The detailed program of the commissioning and testing of works in accordance with the contractor implementation program.
    • The conditions of commissioning such as the state and the availability of the electric network, interface with other works in progress
    • Environmental, health and safety standards and procedures to be adopted.
    • Planning of outages required for pre-commissioning, spot checks and other site tests

During commissioning, the Consultant shall also:

 

  • Coordinate all testing to be done by the contractors, approve the procedures and results announced.
  • Ensure that the contractors conform to the quality and methodology required for the presentation of the commissioning test reports
  • Approve the commissioning test report prepared by the contractors
  • Ensure that the commissioning test report shall be signed jointly by the Consultant, the Client and the contractor
  • Collect a set of documents of the recorded commissioning test results.
  • Issue Interim Work Completion Certificate for the Project works carried out under NTP-TR5G and NTP-TR5E

 

After completion of commissioning works, the Consultant shall have to:

 

  • Verify and approve the "as-built" drawings provided by the contractors
  • Examine and confirm the adequacy of the operating and maintenance manuals provided by the contractors.
  • Issue Final Work Completion Certificate for the Project works carried out under NTP-TR5G and NTP-TR5E

 

3.5       Transfer of Know-How

 

The transfer of know-how shall be carried out at different levels:

 

  1. Transfer of know-how through the work on-site of Employer's engineers working with the Consultant's experts.
  2. Transfer of know-how through training sessions or lectures conducted.
    • The Consultant's Engineers on-site would ensure active collaboration and participation of TCN engineers throughout the project assignment.
    • A well-organized two (2) week Classroom Training of twenty (20) Employer's staff on all aspects of Project Management and Contract Administration
    • Computerized Transmission Line Design (PLS-CADD Hands-On Training)
    • Use of LiDAR to improve reliability using PLS-CADD­­­ (thorough examination of PLS-CADD to improve reliability and utilization, including reconductoring and line re-rating)

 

The objective of the capacity training is to build and reinforce the capacity of the Client in implementing projects of such nature. Other key areas where the training of the Clients PIU Personnel should cover include the use of project planning software for effective monitoring of projects, project scheduling, change management, managing project cost.  In addition, the Consultant may propose in his proposal other relevant areas of learning for consideration by the Client. 

 

3.6       Defects Liability Period (DLP)    

 

The Defect liability period (DLP) is planned to be twelve (12) months after provisional take-over. During this period, the Consultant shall from his head office answer questions via e-mail and fax correspondence from the home office.

 

By the end of the DLP, the Consultant and his specialists shall be present for the final take-over of the completed Project works carried out under NTP-TR5G and NTP-TR5E Contracts separately.  The Consultant shall be consulted on matters related to the execution of the two contracts throughout the DLP.

 

4.0       REQUIREMENTS FOR THE FIRM

 

            The firm is required to possess the following:

  1. The firm's broad experience and overall competence, including the relevance of the applicant firm's area of core business to the assignment envisaged.
  2. Firm's good reputation, strong institutional capacity, and capability in terms of technical expertise, managerial expertise, quality management system, number of technical staff and financial soundness.
  3. The extent of specific experience in assignments of similar nature and complexity in construction management and supervision of Transmission Lines (132kV and above), including review of design, supervision of EPC contractor's quality, schedule, environmental, safety and health compliance, verification of equipment quality, certification of variation orders etc. (relevant completion certificates and letters of recommendations from former clients to be provided if available);
  4. The extent of specific experience in assignments of similar nature and complexity in construction management and supervision of transmission lines in the sub-Africa region would be a plus.
  5. Evidence and certification of quality and environmental management

 

5.0       THE CONSULTANT TEAM

 

The Consultant shall set up his organization team complying with the project needs, and all positions will be held by qualified and skilled staff. The Consultant shall work jointly with the Client's PIU.

 

The Consultant shall provide experienced personnel to carry out the assignment throughout the project management and reconductoring supervision services following task/requirement of the Project. These personnel shall be supported by other experts on call (who shall visit the sites as need be).

 

The Consultant shall provide staff on-site for the overall management, procurement/inspection, construction coordination/quality assurance and testing/commissioning of the facilities on the Project as may be required.  The Minimum qualifications for key staff of Consultant are as follows

 

5.1       Requirements of Key Personnel

 

The team must have suitably qualified personnel to fill the relevant under-listed positions as detailed in the following table.

 

 

 

 

 

Personnel

Total Experience (Years)

In Similar Works (Years)

Number of Key Staff required

Project Manager

15

5

1

Asst. Project Manager

12

5

1

Transmission Line Design Expert

15

5

1

Quality Assurance Expert

10

5

1

Lines Engineer

10

5

5

Civil Engineer

10

5

3

HSE specialist

10

5

5

Protection Engineer

10

5

1

Commissioning Engineer

10

5

1

 

               The Project Manager (Electrical Engineer)

               Must have the following requirements

  • a minimum of 15 years general experience in Transmission Lines works
  • MSc Degree
  • A minimum of 10 years of documentary experience in successful project management and contract supervision of similar nature in developing countries
  • Must always be present in Nigeria for the duration of the project, unless otherwise explicitly agreed

 

               The Assistant Project Manager (Electrical Engineer)

               Must have the following requirements

  • a minimum of 12 years general experience in Transmission Lines works
  • MSc Degree
  • A minimum of 10 years of documentary experience in successful project management and contract supervision of similar nature in developing countries
  • Must always be present in Nigeria for the duration of the project, unless otherwise explicitly agreed

 

Other Key Staff as mentioned above must all have a minimum of 10 years' experience in the construction and/or supervision of turnkey Transmission Lines project of similar nature.

 

Evidence of registration with relevant professional bodies is required in all the cases. A passport photograph of each candidate should be attached.

 

The Consultant shall provide experienced personnel to carry out the assignment throughout the project management services per task/requirement of the Project. These personnel shall be supported by other experts on call (who shall visit the sites as need be).

 

At his head office, the Consultant must have a team in Transmission Lines projects who shall assist the personnel on-site as the need arises.

 

6.0       REPORTS AND TIME SCHEDULE

 

The Consultant shall be required to submit Project monthly, quarterly and completion reports for works carried out under NTP-TR5G and NTP-TR5E Contracts following time schedules.

 

6.1       Project Monthly Report

 

The Consultant shall send a monthly report for each of the contracts to the Employer on the progress of work, including minutes of meetings if the regular site meetings were held for the projects. This report shall be issued in five (5) copies with one (1) electronic copy.

 

6.2       Quarterly Progress Report

 

The Consultant shall send a quarterly report for the projects on the progress of works including the technical execution of the Project, and on the implementation of the environmental measures, the effectiveness and the response of the measures adopted and proposals to amend same if the environmental measures implemented are not given desired results.

 

The Consultant shall also include in the quarterly progress report, financial reports on expenditure & payments made to contractors.

 

This report will be issued in four (4) copies with one (1) electronic copy.

 

6.3       Project Completion Report for NTP-TR5G and NTP-TR5E

 

The Consultant shall prepare a draft Project Completion Report not later than two (2) months after completion of the contracts works.  This report shall include technical and financial aspects and shall be provided first in six (6) copies with soft copies.  The Consultant shall submit for approval to the Employer the texture of this report.  The Employer shall then use one month to make observations which will be incorporated into the draft report before a final version is issued in ten (10) copies together with electronic copies.

 

After the end of the Defects Liability Period, and after final take-over, the Consultant shall update the Project Completion Report that shall become the Final Completion Report which shall be provided in Six (6) copies with electronic copies.

 

7.0       DEADLINE AND LOCAL SERVICES

 

The works required to be carried out under NTP-TR5G and NTP-TR5E Contracts until provisory take-over is estimated to be twenty-four (24) months for the contracts.  The Defects Liability Period shall last for twelve (12) months for the contracts after which the Consultant's services shall be due for completion.

 

 

 

8.0       FACILITIES TO BE PROVIDED BY THE CONSULTANT

 

8.1      Office and Residential Accommodation

The Consultant shall be responsible for the provision of both office and residential accommodation for their staff.

 

8.2     Transportation

The Consultant shall be responsible for their transportation during the Project.

 

9.0       FACILITIES TO BE PROVIDED BY EMPLOYER

 

The Employer shall provide the following to the Consultant:

 

  1. Drawings and documents, such as previous studies, design reports, design calculations, network calculations, etc. established by TCN, the Supplier or other Consultants, before commencement of the Consultant's works which may be required for the performance of the services if available.
  2. Assistance in obtaining permission, licenses for telephones, working permits, residence visas, re-entry and exit visas for the Consultant's staff and families, respectively.
  3. Assistance in facilitating and expediting customs procedures in connection with importation of equipment and materials necessary for the Consultant's services and for the household of the Consultant's key staff and families.

 

10.0     EFFORT LEVEL

 

The expected effort level required for the assignment is 158 man-months

11.0SELECTION METHOD

Consultant shall be selected through the Quality and Cost Based Selection (QCBS) in accordance with the procedures set out in the World Bank’s “Procurement Regulations for IPF Borrowers”January 2017, revised November 2017 and August 2018.

 

12.0COPYRIGHT AND OWNERSHIP

All raw and finished materials would be owned and copyrighted. Permission to use materials by the Consultant for other projects shall require the written permission of the Employer, and the Consultant shall maintain in strict confidence all information received from the Employer concerning imports, financial records and nature of the business.

 

 